Council Chamber remodel is right on schedule!

The Council Chamber remodel is moving along very well. All the rough carpentry, plumbing, and electrical has been completed. The dry wall work has also been completed and is ready for paint. Sullivan Construction started the HVAC work and the installation is approximately 50% done. 

The remaining concrete work is expected to be completed by mid-August. Bobo Construction will then start the installation of the ceiling panels, and Cal Electric will begin the interior lightning. The project is approximately 60% complete. If all goes well, the project is ahead of the anticipated completion date of December 31. 