West Texas Complete Streets Project
Construction updates are listed here chronologically with the most current, or up to date information towards the top!
If you have any questions, feel free to email completestreets@fairfield.ca.gov or call 707-428-7485
Subscribe to this page to receive e-mail and text alerts when new information is posted.
August 19th, 2026
Construction Schedule:
Week of August 17th to August 21st, 2026
- Westbound & Eastbound Outside Lane: Continue installing electrical infrastructure and adjusting utility covers to grade throughout the project site. Begin installation of thermoplastic striping and pavement markings.
Week of August 24th to August 28th, 2026
- Westbound & Eastbound Outside Lane: Continue the installation of electrical infrastructure as well as thermoplastic striping and pavement markings. Complete adjusting utility covers to grade.
Week of August 31st to September 4th, 2026
- Westbound & Eastbound Outside Lane: Continue installation of electrical infrastructure as well as thermoplastic striping and pavement markings. Begin installation of stamped asphalt at crosswalks.
July 16th, 2026
AT&T has completed the replacement of the underground vault on the westbound lane adjacent to the Park Crossing Apartments.
Temporary pedestrian pathways are provided in areas where concrete sidewalks are undergoing replacement to maintain continued access to businesses.
Construction Schedule:
July 20th to July 31st, 2026
Traffic signals will be operating in flash mode at night between 7:00PM and 6:00AM for asphalt grinding and paving operations.
Please keep in mind that when a stop light is flashing red in all directions, it should be approached as a four-way stop intersection.
Week of July 13th to July 17th, 2026
- Westbound & Eastbound Outside Lane: Remove and replace damaged concrete curb and gutter. Adjust utility covers to the new roadway grade. Continue installing electrical infrastructure as well as landscaping in planter areas and medians.
Week of July 20th to July 24th, 2026
- Westbound & Eastbound Outside Lane: Install electrical infrastructure for traffic signals. Begin spot repairs and grinding the existing roadway surface in preparation for paving operations.
June 9th, 2026
Both westbound and eastbound OUTSIDE LANES along West Texas Street, from Pennsylvania Avenue to Beck Avenue, are permanently closed. One lane in each direction, alongside the center lane, will remain open at all times.
July 8th, 2026
Both westbound and eastbound OUTSIDE LANES along West Texas Street, from Pennsylvania Avenue to Beck Avenue, are permanently closed. One lane in each direction, alongside the center lane, will remain open at all times.
Sidewalk on the north side and sections of sidewalk on the south side of West Texas Street are now open to the public. Temporary pedestrian pathways are designated on the south side of the street to ensure continued access to businesses.
Left turns are prohibited at the intersection of West Texas Street and 1st Street as Contractors have installed a median island.
AT&T has begun construction to replace an underground vault on the westbound lane adjacent to the Park Crossing Apartments, closing a segment of the right turn lane to Beck Avenue.
Construction Schedule:
Week of July 6th to July 10th, 2026
- Westbound & Eastbound Outside Lane: Remove and replace damaged concrete curb and gutter. Continue installing electrical infrastructure as well as landscaping in planter areas and medians.
- Westbound Right Turn Lane at Beck Avenue (AT&T Vault Replacement): Install new underground vault/manhole.
Week of July 13th to July 17th, 2026
- Westbound & Eastbound Outside Lane: Adjust existing utility covers in the roadway in preparation for paving operations. Continue installation of electrical infrastructure and equipment.
- Westbound Right Turn Lane at Beck Avenue (AT&T Vault Replacement): Continue installation of new underground vault/manhole.
June 9th, 2026
Both westbound and eastbound OUTSIDE LANES along West Texas Street, from Pennsylvania Avenue to Beck Avenue, are permanently closed. One lane in each direction, alongside the center lane, will remain open at all times.
Sidewalk on the north side and sections of sidewalk on the south side of West Texas Street are now open to the public. Temporary pedestrian pathways are designated on the south side of the street to ensure continued access to businesses.
Left turns are prohibited at the intersection of West Texas Street and 1st Street as Contractors have installed a median island. Please see the attached for alternative routes.
Construction Schedule:
Week of June 22nd to June 26th, 2026
- Westbound & Eastbound Outside Lane: Continue planting landscaping in median islands and installing electrical infrastructure.
- Westbound Right Turn Lane at Beck Avenue (AT&T Vault Replacement): Install new underground vault/manhole.
Week of June 29th to July 3rd, 2026
- Westbound & Eastbound Outside Lane: Continue installation of electrical infrastructure and equipment.
- Westbound Right Turn Lane at Beck Avenue (AT&T Vault Replacement): Continue installation of new underground vault/manhole.
Week of July 6th to July 10th, 2026
- Westbound & Eastbound Outside Lane: Continue installing electrical infrastructure and equipment.
- Westbound Right Turn Lane at Beck Avenue (AT&T Vault Replacement): Reinforce the new underground vault/manhole with the installation of rebar.
May 27th, 2026
Both westbound and eastbound OUTSIDE LANES along West Texas Street, from Pennsylvania Avenue to Beck Avenue, are permanently closed. One lane in each direction, alongside the center lane, will remain open at all times.
Sidewalk on the north side of West Texas is now open to the public. Temporary pedestrian pathways are designated on the south side of the street to ensure continued access to business.
AT&T has begun construction to replace an underground vault on the westbound lane adjacent to the Park Crossing Apartments, closing a segment of the right turn lane to Beck Avenue.
NO LEFT TURNS WILL BE ALLOWED AT THE INTERSECTION OF WEST TEXAS STREET AND 1ST STREET as Contractors install a median island. Please see the attached below for alternative routes.
Construction Schedule:
Week of May 26th to May 29st, 2026
- Westbound & Eastbound Outside Lane: Install electrical infrastructure and equipment Minor work anticipated in planter areas to install new landscaping and topsoil.
- Westbound Right Turn Lane at Beck Avenue (AT&T Vault Replacement): Removing existing manhole underground vault.
Week of June 1st to June 5th, 2026
- Westbound & Eastbound Outside Lane: Continue installation of electrical infrastructure and equipment as well as new landscaping and topsoil in planter areas.
- Westbound Right Turn Lane at Beck Avenue (AT&T Vault Replacement): Replace underground conduits and prepare new manhole.
Week of June 8th to June 12th, 2026
- Westbound & Eastbound Outside Lane: Continue installation of electrical infrastructure and equipment throughout the West Texas Street corridor.
- Westbound Right Turn Lane at Beck Avenue (AT&T Vault Replacement): Construct new manhole and prepare for new vault construction.
April 30th, 2026
Both westbound and eastbound OUTSIDE LANES along West Texas Street, from Pennsylvania Avenue to Beck Avenue, are permanently closed. One lane in each direction, alongside the center lane, will remain open at all times.
Sidewalk on the north side of West Texas is now open to the public. Temporary pedestrian pathways are designated on the south side of the street to ensure continued access to business.
NO LEFT TURNS WILL BE ALLOWED AT THE INTERSECTION OF WEST TEXAS STREET AND 1ST STREET as Contractors begin the installation of a median island. Please see the attached below for alternative routes.
Construction Schedule:
Week of April 27th to May 1st, 2026
- Westbound Outside Lane: Minor work anticipated in planter areas.
- Eastbound Outside Lane: Install irrigation and topsoil in new planter areas. Begin demolition for the new median island on West Texas Street, between Pennsylvania Avenue and 5th Street.
Week of May 4th to May 8th, 2026
- Westbound Outside Lane: Minor work anticipated in planter areas.
- Eastbound Outside Lane: Continue installation of irrigation and topsoil in new planter areas. Install electrical infrastructure. Continue demolition for median island on West Texas Street, between Pennsylvania Avenue and 5th Street, and begin concrete installation when ready. Plant trees in new planter areas.
Week of May 11th to May 15th, 2026
- Westbound Outside Lane: Minor work anticipated in planter areas.
- Eastbound Outside Lane: Continue installation of electrical infrastructure. Excavate to install topsoil in the median islands on West Texas Street, between Pennsylvania Avenue and 5th Street. Continue planting trees in new planter areas.
April 16th, 2026
Both westbound and eastbound OUTSIDE LANES along West Texas Street, from Pennsylvania Avenue to Beck Avenue, are permanently closed. One lane in each direction, alongside the center lane, will remain open at all times.
Sidewalk on the north side of West Texas is now open to the public. Temporary pedestrian pathways are designated on the south side of the street to ensure continued access to business.
APRIL 27, 2026: NO LEFT TURNS WILL BE ALLOWED AT THE INTERSECTION OF WEST TEXAS STREET AND 1ST STREET as Contractors begin the installation of a median island. Please see the attached below for alternative routes.
Week of April 13th to April 17th, 2026
- Westbound Outside Lane: Minor work anticipated in planter areas.
- Eastbound Outside Lane: Install irrigation and topsoil in new planter areas. Install concrete sidewalk, curb and gutter when complete.
Week of April 20th to April 24th, 2026
- Westbound Outside Lane: Minor work anticipated in planter areas.
- Eastbound Outside Lane: Install irrigation and topsoil in new planter areas. Complete minor asphalt restoration alongside the installation of concrete sidewalk, curb and gutter.
Week of April 27th to May 1st, 2026
- Westbound Outside Lane: Minor work anticipated in planter areas.
- Eastbound Outside Lane: Install irrigation and topsoil in new planter areas.
April 8th, 2026
Both westbound and eastbound OUTSIDE LANES along West Texas Street, from Pennsylvania Avenue to Beck Avenue, are permanently closed. One lane in each direction, alongside the center lane, will remain open at all times.
Sidewalk on the north side of West Texas is now open to the public. Temporary pedestrian pathways are designated on the south side of the street to ensure continued access to business.
Construction Schedule:
Week of April 6th to April 10th, 2026
- Westbound Outside Lane: Minor work anticipated in planter areas.
- Eastbound Outside Lane: Continue installation of irrigation and topsoil in new planter areas. Install underground infrastructure. Prepare for the installation of concrete sidewalk, curb, and gutter when complete.
Week of April 13th to April 17th, 2026
- Westbound Outside Lane: Minor work anticipated in planter areas.
- Eastbound Outside Lane: Install irrigation and topsoil in new planter areas. Install concrete sidewalk, curb and gutter when complete.
Week of April 20th to April 24th, 2026
- Westbound Outside Lane: Minor work anticipated in planter areas.
- Eastbound Outside Lane: Install irrigation and topsoil in new planter areas. Complete minor asphalt restoration alongside the installation of concrete sidewalk, curb and gutter.
March 19th, 2026
With left turns onto and from West Texas at 1st Street restricted, drivers traveling eastbound on West Texas Street are expected to use nearby neighborhood streets to reach Fairview Elementary School. The most likely alternate routes include 2nd Street to Empire Street to 1st Street, or Pennsylvania Avenue to Empire Street to 1st Street.
While passenger vehicle traffic on Empire is expected to rise, the residential layout should keep heavy trucks away, as there are no commercial sites in the immediate area to draw them in. Trucks are encouraged to avoid West Texas Street as a primary route and instead use Travis Boulevard from Interstate 80 or Pennsylvania Avenue from State Route 12.
March 11th, 2026
Both westbound and eastbound OUTSIDE LANES along West Texas Street, from Pennsylvania Avenue to Beck Avenue, are permanently closed. One lane in each direction, alongside the center lane, will remain open at all times.
Sidewalk on the north side of West Texas is now open to the public. Temporary pedestrian pathways are designated on the south side of the street to ensure continued access to business.
Construction Schedule:
Week of March 9th to March 13th, 2026
- Westbound Outside Lane: Minor work anticipated in planter areas.
- Eastbound Outside Lane: Install irrigation and topsoil in new planter areas. Prepare for installation of concrete sidewalk, curb and gutter when complete.
Week of March 16th to March 20th, 2026
- Westbound Outside Lane: Minor work anticipated in planter areas.
- Eastbound Outside Lane: Continue installation of irrigation and top soil in new planter areas. Prepare for installation of concrete sidewalk, curb and gutter when complete.
Week of March 23rd to March 27th, 2026
- Westbound Outside Lane: Minor work anticipated in planter areas.
- Eastbound Outside Lane: Install irrigation and topsoil in new planter areas. Prepare for installation of concrete curb and gutter when complete.
March 4th, 2026
Both westbound and eastbound OUTSIDE LANES along West Texas Street, from Pennsylvania Avenue to Beck Avenue, are permanently closed. One lane in each direction, alongside the center lane, will remain open at all times.
Sidewalk on the north side of West Texas is now open to the public. Temporary pedestrian pathways are designated on the south side of the street to ensure continued access to business.
Construction Schedule:
Week of March 3rd to March 6th, 2026
- Westbound Outside Lane: Continue reconnection of private driveways to the new city-installed driveway.
- Eastbound Outside Lane: Install underground drainage infrastructure on Gregory Lane as well as Allan Witt Park. Prepare for installation of curb and gutter when complete.
Week of March 9th to March 13th, 2026
- Westbound Outside Lane: Minor work anticipated in planter areas.
- Eastbound Outside Lane: Install irrigation and topsoil in new planter areas. Prepare for installation of concrete sidewalk, curb and gutter when complete.
Week of March 16th to March 20th, 2026
- Westbound Outside Lane: Minor work anticipated in planter areas.
- Eastbound Outside Lane: Continue installation of irrigation and top soil in new planter areas. Prepare for installation of concrete sidewalk, curb and gutter when complete.
February 4th, 2026
Both westbound and eastbound OUTSIDE LANES along West Texas Street, from Pennsylvania Avenue to Beck Avenue, are permanently closed. One lane in each direction, alongside the center lane, will remain open at all times.
Temporary pedestrian pathways are designated along the street to ensure continued access.
Construction Schedule:
**Weather Dependent**
February 16th, 2026 (Presidents Day)
- No construction will take place over the Presidents Day holiday, however, traffic control devices will remain in place for public safety.
Week of February 2nd to February 6th, 2026
- Westbound Outside Lane: Contractors to complete minor improvements in new planter areas.
- Eastbound Outside Lane: Continue installation of underground drainage infrastructure. Prepare for installation of concrete sidewalk, curb, and gutter when complete.
Week of February 9th to February 13th, 2026
- Westbound Outside Lane: Reconnect private driveways to the new city-installed driveway.
- Eastbound Outside Lane: Install concrete sidewalk, curb, and gutter.
Week of February 17th to February 20th, 2026
- Westbound Outside Lane: Contractors to complete minor improvements in new planter areas.
- Eastbound Outside Lane: Install concrete curb and gutter.
January 28th, 2026
Both westbound and eastbound OUTSIDE LANES along West Texas Street, from Pennsylvania Avenue to Beck Avenue, are permanently closed. One lane in each direction, alongside the center lane, will remain open at all times.
Temporary pedestrian pathways are designated along the street to ensure continued access.
Construction Schedule:
**Weather Dependent**
Week of January 26th to January 30th, 2026
- Westbound Outside Lane: Continue installation of irrigation infrastructure and topsoil in planter areas.
- Eastbound Outside Lane: Install aggregate base for sidewalk installation.
Week of February 2nd to February 6th, 2026
- Westbound Outside Lane: Reconnect private driveways to the new city-installed driveway. Install irrigation and topsoil in planter areas.
- Eastbound Outside Lane: Continue installation of underground drainage infrastructure as well as streetlight conduit. Install aggregate base for sidewalk installation when complete.
Week of February 9th to February 13th, 2026
- Westbound Outside Lane: Reconnect private driveways to the new city-installed driveway. Install remaining irrigation infrastructure and topsoil in planter areas. Place aggregate base for sidewalk installation when complete.
- Eastbound Outside Lane: Continue installation of irrigation infrastructure and topsoil in plater areas. Install underground drainage infrastructure, landscaping irrigation sleeves, as well as street light conduit and foundations.
January 21st, 2026
Both westbound and eastbound OUTSIDE LANES along West Texas Street, from Pennsylvania Avenue to Beck Avenue, are permanently closed. One lane in each direction, alongside the center lane, will remain open at all times.
Temporary pedestrian pathways are designated along the street to ensure continued access.
Construction Schedule:
**Weather Dependent**
Week of January 19th to January 23rd, 2026
- Westbound Outside Lane: Install irrigation and topsoil in planter areas. Complete installation of remaining concrete sidewalk, curb and gutter as well as minor pavement restoration.
- Eastbound Outside Lane:
- Begin grinding operations to remove existing asphalt. Install underground drainage infrastructure.
Week of January 26th to January 30th, 2026
- Westbound Outside Lane: Continue installation of irrigation infrastructure and topsoil in planter areas near. Install concrete curb and gutter when complete.
- Eastbound Outside Lane: Continue installation of underground drainage infrastructure. Install 2” conduit and foundations for street light installation.
Week of February 2nd to February 6th, 2026
- Westbound Outside Lane: Reconnect private driveways to the new city-installed driveway.
- Eastbound Outside Lane: Continue installation of underground drainage infrastructure as well as installation of streetlight conduit.
January 7th, 2026
Both westbound and eastbound OUTSIDE LANES along West Texas Street, from Pennsylvania Avenue to Beck Avenue, are permanently closed. One lane in each direction, alongside the center lane, will remain open at all times.
Temporary pedestrian pathways are designated along the street to ensure continued access.
Construction Schedule:
**Weather Dependent**
Week of January 5th to January 9th, 2026
- Westbound Outside Lane: Continue installation of underground drainage infrastructure. Install irrigation and soil in planter areas. Install sidewalk, curb, and gutter when complete.
- Eastbound Outside Lane: No construction activities anticipated in eastbound travel lanes. The outside right lane will remain closed for public safety.
Week of January 12th to January 16th, 2026
- Westbound Outside Lane: Install concrete sidewalk, curb, and gutter.
- Eastbound Outside Lane: Demolish existing concrete sidewalk. Begin grinding operations to remove existing asphalt.
Week of January 19th to January 23rd, 2026
- Westbound Outside Lane: Install underground drainage infrastructure near Allan Witt Park. Install irrigation infrastructure and soil for planter areas. Complete minor pavement restoration.
- Eastbound Outside Lane: Continue grinding operations to remove existing asphalt.
December 10th, 2025
Both westbound and eastbound OUTSIDE LANES along West Texas Street, from Pennsylvania Avenue to Beck Avenue, are permanently closed. One lane in each direction, alongside the center lane, will remain open at all times.
Temporary pedestrian pathways are designated along the street to ensure continued access.
December 25 - December 26, 2025
No construction will take place over the Christmas holiday, however lane closures and sidewalk detours will remain in place for public safety.
Construction Schedule:
**Weather Dependent**
Week of December 1st to December 5, 2025
- Westbound Outside Lane: Continue installation of underground drainage infrastructure. Prepare and install concrete curb and gutter when complete. Install irrigation lines and begin planting when complete.
- Eastbound Outside Lane: Continue survey and bore operations to install conduit for fiber optic lines.
Week of December 8th to December 12th, 2025
- Westbound Outside Lane: Continue installation of underground drainage infrastructure. Install irrigation infrastructure and continue planting when complete. Complete minor pavement restoration.
- Eastbound Outside Lane: Continue survey and bore operations to install remaining conduit for fiber optic lines.
Week of December 15th to December 19th, 2025
- Westbound Outside Lane: Continue installation of underground drainage infrastructure. Prepare for installation of sidewalk, curb, and gutter when complete. Continue installation of irrigation lines and begin planting when complete.
- Eastbound Outside Lane: No construction activities anticipated in eastbound travel lanes. The outside right lane will remain closed for public safety.
Week of December 22nd 2025 to December 24th, 2025
- Westbound Outside Lane: Continue installation of underground drainage infrastructure. Prepare for installation of sidewalk, curb, and gutter when complete.
- Eastbound Outside Lane: No construction activities anticipated in eastbound travel lanes. The outside right lane will remain closed for public safety.
November 12th, 2025
Both westbound and eastbound OUTSIDE LANES along West Texas Street, from Pennsylvania Avenue to Beck Avenue, are permanently closed. One lane in each direction, alongside the center lane, will remain open at all times.
Temporary pedestrian pathways are designated along the street to ensure continued access.
November 27th and November 28th, 2025
No construction will take place over the Thanksgiving holiday, however lane closures and sidewalk detours will remain in place for public safety.
Construction Schedule:
**Weather Dependent**
Week of November 10th to November 14th, 2025
- Westbound Outside Lane: Continue installation of underground drainage infrastructure. Install curb and gutter when complete.
- Eastbound Outside Lane: Continue bore operations to install conduit for fiber optic lines.
Week of November 17th to November 21st, 2025
- Westbound Outside Lane: Continue installation of underground drainage infrastructure. Install irrigation infrastructure. Install concrete curb and gutter when complete. Prepare for sidewalk installation.
- Eastbound Outside Lane: Continue bore operations to install remaining conduit for fiber optic lines.
Week of November 24th to November 26th, 2025
- Westbound Outside Lane: Continue installation of underground drainage infrastructure. Install concrete curb and gutter and prepare for sidewalk installation when complete.
- Eastbound Outside Lane: No construction activities anticipated in eastbound travel lanes. The outside right lane will remain closed for public safety.
October 27th, 2025
Both westbound and eastbound OUTSIDE LANES along West Texas Street, from Pennsylvania Avenue to Beck Avenue, are permanently closed. One lane in each direction, alongside the center lane, will remain open at all times.
Temporary pedestrian pathways are designated along the street to ensure continued access.
Construction Schedule:
Week of October 20th to October 24th, 2025
- Westbound Outside Lane: Install underground drainage infrastructure and prepare for curb and gutter installation when complete. Complete fire hydrant relocations.
- Eastbound Outside Lane: Complete remaining pothole survey to verify utility conflicts. Once verified, contractor's will bore to place conduit for fiber optic lines.
Week of October 27th to 31st, 2025
- Westbound Outside Lane: Install underground drainage infrastructure. Prepare and install sidewalk, curb, and gutter installation when complete.
- Eastbound Outside Lane: Bore to install conduit for fiber optic lines.
Week of November 3rd to November 10th, 2025
- Westbound Outside Lane: Install underground drainage infrastructure. Install sidewalk, curb, and gutter installation when complete.
- Eastbound Outside Lane: Bore to install conduit for fiber optic lines
October 15, 2025
Both westbound and eastbound OUTSIDE LANES along West Texas Street, from Pennsylvania Avenue to Beck Avenue, are permanently closed. One lane in each direction, alongside the center lane, will remain open at all times.
Temporary pedestrian pathways are designated along the street to ensure continued access.
Construction Schedule:
**Weather Dependent**
Week of October 6th to October 10th, 2025
- Westbound Outside Lane: Continue the preparation and construction of the sidewalk.
- Eastbound Outside Lane: Complete remaining pothole survey to verify utility conflicts. Once verified, contractor's will bore to place conduit for fiber optic lines.
Week of October 13th to 17th, 2025
- Westbound Outside Lane: Complete fire hydrant relocations. Continue preparation and installation of sidewalk. Install underground drainage infrastructure and prepare for curb and gutter installation when complete.
- Eastbound Outside Lane: Complete remaining pothole survey to verify utility conflicts. Once verified, contractor's will bore to place conduit for fiber optic lines.
Week of October 20th to October 24th, 2025
- Westbound Outside Lane: Continue sidewalk construction. Continue installation of underground drainage infrastructure and prepare for curb and gutter construction when complete and begin asphalt removal.
- Eastbound Outside Lane: Complete remaining pothole survey to verify utility conflicts. Once verified, contractor's will bore to place conduit for fiber optic lines.
October 6, 2025
Both westbound and eastbound OUTSIDE LANES along West Texas Street, from Pennsylvania Avenue to Beck Avenue, are permanently closed. One lane in each direction, alongside the center lane, will remain open at all times.
Temporary pedestrian pathways are designated along the street to ensure continued access.
Construction Schedule:
Week of September 29th to October 3rd, 2025
- Westbound Outside Lane: Continue the installation of street light conduit, landscaping sleeves and foundations. Begin constructing new sidewalk and drainage infrastructure under the curb and gutter.
- Eastbound Outside Lane: Complete remaining pothole survey to verify utility conflicts. Once verified, contractor's will bore to place conduit for fiber optic lines.
Week of October 6th to 10th, 2025
- Westbound Outside Lane: Install underground drainage infrastructure. Continue the installation of street light conduit, landscaping sleeves, and foundations. Relocate remaining fire hydrants and prepare for sidewalk installation when complete.
- Eastbound Outside Lane: Complete remaining pothole survey to verify utility conflicts. Once verified, contractor's will bore to place conduit for fiber optic lines.
Week of October 13th to October 17th, 2025
- Westbound Outside Lane: Install underground drainage infrastructure and prepare for sidewalk installation when complete.
- Eastbound Outside Lane: Complete remaining pothole survey to verify utility conflicts. Once verified, contractor's will bore to place conduit for fiber optic lines.
September 18th, 2025
Both westbound and eastbound OUTSIDE LANES along West Texas Street, from Pennsylvania Avenue to Beck Avenue, are permanently closed. One lane in each direction, alongside the center lane, will remain open at all times.
Temporary pedestrian pathways are designated along the street to ensure continued access.
Construction Schedule:
Week of September 8th to September 12th, 2025
- Westbound Outside Lane: Install streetlight conduit and foundations as well as underground drainage infrastructure; continue fire hydrant relocations; continue concrete and asphalt demolition.
- Eastbound Outside Lane: Continue potholing to verify existing utility conflicts; install streetlight conduit and foundations; continue concrete and asphalt demolition.
Week of September 15th to September 19th, 2025
- Westbound Outside Lane: Install street light conduit, foundations and underground drainage infrastructure. Begin concrete demolition between 5th Street and Beck Avenue.
- Eastbound Outside Lane: Continue pothole survey.
Week of September 22nd to September 26th, 2025
- Westbound Outside Lane: Install drainage infrastructure and backfill in preparation for sidewalk installation.
- Eastbound Outside Lane: Complete remaining pothole survey and begin bore operations to install conduit for fiber optic lines.
Week of September 29th to October 3rd, 2025
- Westbound Outside Lane: Install street light conduit, foundations, and underground drainage infrastructure. Backfill in preparation for sidewalk installation.
- Eastbound Outside Lane: Continue bore operations for conduit installation. Remove asphalt and install underground drainage infrastructure.
September 1, 2025
No construction will take place over the Labor Day holiday, however lane closures and sidewalk detours will remain in place to ensure public safety.
August 26, 2025
Both westbound and eastbound OUTSIDE LANES along West Texas Street, from Pennsylvania Avenue to Beck Avenue, are permanently closed.
Construction Schedule:
Week of August 25th to August 29th, 2025
- Pennsylvania Avenue to Beck Avenue (Westbound outside lane): Continue installation of drainage infrastructure, relocating fire hydrants, and new irrigation.
- Beck Avenue to Pennsylvania Avenue (Eastbound outside lane): Lane closure to install storm drainage infrastructure and new irrigation.
Week of September 2nd to September 5th, 2025
- Pennsylvania Avenue to Beck Avenue (Westbound outside lane): Continue installation of underground drainage infrastructure and new irrigation.
- Beck Avenue to Pennsylvania Avenue (Eastbound outside lane): Continue installation of storm drainage infrastructure and new irrigation.
August 18, 2025
The westbound outside lane along West Texas Street, from Pennsylvania Avenue to Beck Avenue, is closed permanently.
Beginning permanent closure of the eastbound outside lane; starting at Beck Avenue and continuing east.
Construction Schedule:
Week of August 18th to August 22nd, 2025
- Pennsylvania Avenue to Beck Avenue (Westbound outside lane): Continued concrete and pavement demolition along the westbound outside lane.
- Beck Avenue to Pennsylvania Avenue (Eastbound outside lane): Closure to complete remaining survey work and subsequently begin concrete demolition.
Week of August 25th to August 29th, 2025
- Pennsylvania Avenue to Beck Avenue (Westbound outside lane):Install underground drainage infrastructure and relocate existing fire hydrants.
- Beck Avenue to Pennsylvania Avenue (Eastbound outside lane): Continue concrete demolition.
August 6, 2025
Traffic Advisory during Construction of Project
Please be advised that there will be an increase in traffic congestion along West Texas Street due to construction activities.
Important Notes:
- West Texas Street and all local business will remain open with full driveway access during construction.
- Outside lane closures will be implemented gradually as construction progresses.
The first day of school is August 13, 2025. Please refer to the new traffic route map for Fairview Elementary:
New Traffic Routes - Fairview Elementary
Nuevas Rutas de Tráfico - Fairview Elementary
Construction Schedule:
Week of August 4th to August 8th, 2025
- Close westbound West Texas Street outside lane (5th Street to Beck Avenue) for potholing and surveying.
- Construction will be from Beck Avenue to 2nd Street.
Week of August 11th to August 15th, 2025
- Close eastbound West Texas Street outside lane (Gregory Lane to Pennsylvania Avenue) for final surveying; then start demolition.
- Continue lane closure on westbound West Texas Street outside lane (Beck Avenue to Pennsylvania Avenue).
July 25, 2025
Route 1 Bus Stops along West Texas Street Closed during Construction Project
Starting Monday, July 28th, Route 1 bus stops between Beck Ave. and Pennsylvania Ave. will be closed due to construction on West Texas St.
Route 1 riders are urged to board at:
- Outbound: the Fairfield Transportation Center or temporary stop at Woolner Ave. and Enterprise Dr.
- Inbound: temporary stops at Woolner Ave and Enterprise Dr, and Pennsylvania Ave. and Broadway St.
This detour will remain in effect until project completion, projected for Summer 2026.
Visit www.fasttransit.org for real time-updates, bus schedules, and detour maps.
For more information, contact (707) 434-3800 or dispatch at (707) 422-2877.
July 14th, 2025
You're Invited to a Community Meeting
Date: July 22, 2025
Time: 6:00 PM – 7:30 PM
Location: Community Center – Lakeside Rooms A & B
Join us for an important community meeting to learn more about the upcoming construction project and how it will impact and benefit the neighborhood. This collaborative event will feature updates and resources from multiple City departments, including:
- Learn about construction schedules, traffic impacts, and the improvements being made to enhance safety and accessibility.
- Discover support programs and resources available to help small businesses during construction.
- Explore how this project supports the Heart of Fairfield Specific Plan and aligns with the City’s long-term vision and goals.
April 15, 2025
On April 15, 2025, the City Council awarded a construction contract to Ghilotti Brothers, Inc. for project. The total contract amount is $10,084,965.
West Texas Street is an important roadway connecting I-80 to downtown Fairfield and its community destinations including shopping centers, schools, regional parks, city and county government headquarters, a performing arts center, and an aquatics complex. This commercial corridor also links residents to key transportation hubs, such as the intermodal Fairfield Transportation Center and Suisun-Fairfield train station.
West Texas Street became a local street when Caltrans rerouted Highway 12 and relinquished the right-of-way for the former Highway 12 to the city in the mid-1990s. With the growth of the city and the re-routing of the highway, it now serves as a local road, however it needs to serve both commercial needs and the needs of residents who do not own cars, or rely on bicycles, walking, and mass transit.
The proposed complete-street improvements will make the roadway safer, which will encourage more people to bicycle and walk. Newer, better-designed mixed-use corridors will attract new residents, jobs, and commercial development.
Project Elements
The project will be reducing the number of lanes on West Texas Street from the five-lane highway to a three-lane complete street design. Installation of Class IV separated bikeways, widened sidewalks, landscaped buffers, and two additional marked crossings: one new traffic signal at 2nd Street and one rectangular rapid flashing beacon near 1st Street.
Click here to view the full set of plans for the West Texas Street Complete Streets Project
Project Benefits
- Cements the downtown core as the cultural heart of the city for business, entertainment, and residential uses.
- Answers the call by residents to increase safety on West Texas Street.
- Provides safe routes to school for students on foot and bicycle.
- Spurs private investment into the corridor.
- Provides better access to two vital transportation hubs (the Fairfield Transportation Center and the Suisun-Fairfield train station).
- Reduces collisions on a stretch of roadway that has inordinately high rates of collisions between vehicles and bicycles or pedestrians.
- Increases transit use, along with more pedestrian and bicycle trips, resulting in greenhouse gas reductions for the city.
- Urban landscape parkway encourages people to walk more and stay active, which is beneficial for both their physical health and their mental happiness.
- Properties close to parks and abundant landscaping tend to increase property value as people find it appealing when looking to buy or rent a place.
-
$2.0 Million for conceptual planning, environmental clearance, design, and preparation of plans, specifications, and engineer’s estimates.
-
$11,597,710 budgeted for construction (Ghilloti Bros., contract + 15% contingency)
How does West Texas Complete Street work?
Funding
The total cost of the project is estimated over $20 Million.
Funding for the project is provided through state and regional grants, and local contributions. In 2021, the project was awarded $10.9 million in state grant funds through the Active Transportation Program administered by Caltrans. The project was awarded $1.37 million in Regional Transportation Impact Fee from the Solano Transportation Authority. The remaining funds are contributed from Senate Bill 1 Road Maintenance and Rehabilitation Program and local contributions.
Construction will start July 2025 and anticipated to continue through July 2026. Please note that this schedule is subject to change depending on weather, unanticipated circumstances, and seasonal access restrictions to creek areas. Work will typically take place 7:00 a.m. to 7:00 p.m. from Monday through Friday. On occasion, if deemed necessary and as approved by the city, periodic night work and/or weekend work may be necessary. Prior notice will be given for night work, and if periodic weekend work is needed.
This construction includes significant roadway excavation, paving, landscaping, traffic signal installation, and sidewalk improvements. As with all large construction projects, there will be unavoidable disruptions to nearby businesses, neighbors and to motorists traveling in the area. We apologize in advance for noise, dust, lane closures, traffic delays, and any other impacts or inconveniences.
When driving in the area, always be aware of construction crews and equipment, flaggers, special signage, slower traffic, and rough roadway. Follow all special directions from signs and crews and never travel faster than is safe for the conditions. If possible, use an alternative route to avoid traffic delays.
Thank you for your cooperation and patience as we work to widen and improve this important roadway.
Why is the City of Fairfield pursuing the West Texas Complete Streets Project?
The project is an outgrowth of the Heart of Fairfield Specific Plan and public input received during the formation of that Plan. The proposed complete-street improvements will provide better designed mixed-use corridors, will improve connections to the downtown area, attract new residence jobs and commercial developments, make the roadway safer, and encourage more people to bike and walk.
Why did the city reduce traffic lanes and dedicated bike lanes when there were not many who ride bikes in W Texas?
There are a surprising number of bicyclists on West Texas and the implementation of the Heart of Fairfield Specific Plan is expected to draw an even greater number. In addition, the incidents of car vs. bicycle crashes along the section of West Texas were statistically significant. Protected Class IV bike lanes were needed to provide the needed bicycle safety. The decrease in the number of through vehicle lanes helped accomplish the Plans goal of traffic calming and reduced speeds and crashes.
Would reducing lanes results in fewer cars driving by and fewer customers?
Reducing lanes was a key part of achieving the safety goals outlined in the Heart of Fairfield Specific Plan. While the new design includes fewer lanes, it improves traffic flow by clearly separating different transportation modes and reducing conflict points. Traffic modeling—based on real-world data—shows that the street’s capacity remains comparable to the previous layout.
A similar redesign in downtown Fairfield in 2022, which included all-way stops, defined bike lanes, and traffic calming features, has already proven successful. These changes not only enhanced safety but also slowed traffic enough for drivers to better notice and access local businesses. Since then, downtown has welcomed seven new restaurants, experienced higher foot traffic, and become a more vibrant commercial area.
We expect West Texas to experience similar economic and community benefits following the completion of these improvements.
Why were there medians installed, preventing turns left between Pennsylvania and 1st Street but not at other locations?
Center medians by their nature prohibit left turns but are needed is some instances to are important where needed to improve safety and traffic flow. An analysis of data showed that the block between 1st Street and Pennsylvania Avenue had a very high rate of collisions, particularly serious collisions. Based on a review of 5-years’ worth of data, 35% of crashes and 65% of fatalities along the entire stretch of the project occurred in this block and many involved turns into or out of driveways. This section of West Texas Street also has a school crossing. Based on the data, a center median in this block was necessary to address this history of issues and provide needed safety for all mode of transportation.
Why did the City choose plastic bollards (K71 Post) instead of a raised curb for the Class IV Bike Lanes? Class IV bike lanes require some type of vertical barrier to help protect bicyclists.
The two most common types are curbs and flexible delineators. For West Texas Street, curbs were not an attractive option because they would impede drainage from the street and create potential traffic safety problems. Flexible delineators were a better complement to the design of the roadway. The City chose the K71 Post over standard delineators as they are more aesthetically pleasing and offer greater protection due to their size.
What is a bike box and how do you use it? This is a new design for Fairfield where both Drivers and Bicyclist will need education.
Bike boxes are safety improvements for cyclists. A "bike box" is a designated area painted on the road at a traffic light intersection, allowing cyclists to position themselves ahead of car traffic when waiting for a green light. This increases the visibility of cyclists and helps to minimize collision risks, particularly from right-turning vehicles.
Utility Relocation Project- Completed
As part of the West Texas Complete Streets Project, the City of Fairfield will replace the old water main along West Texas Street from just west of Curtis Drive to Pennsylvania Avenue starting October 1. The Utility Relocation Project will involve installing a new water main on the north side of the street and new water, irrigation, and fire hydrant services for all adjacent properties.
During construction, you may experience temporary driveway access restrictions, noise, dust, and poor air quality. For your safety, please pay attention to posted signs and flaggers. Construction hours will be Monday - Friday from 7 am to 5 pm.
West Texas Street Utility Relocation Project - Thursday, January 30, 2025
During the week of January 27th, the Public Works Department and its contractor made great progress on the installation of the new waterline in West Texas Street. The following are key updates:
- Water Main Installation: The 12” water main, service lines, stub streets, and backflow devices have been successfully installed, tested, chlorinated, and tied into the system.
- Service Box & Backfill Work: Crews are currently setting service boxes and completing backfill work on the private side.
- Sidewalk & Road Restoration: Work is underway to restore sidewalks and roadways affected by the project.
The contractor is slated to complete construction mid-March, depending on weather.
West Texas Street Utility Relocation Project - Wednesday, December 11, 2024
The Public Works Department, in collaboration with its contractor, Cratus, is pleased to announce a significant milestone in the ongoing construction on West Texas Street. This week, preliminary flushing and chlorination are being performed on the newly installed water main. These essential procedures are critical to ensuring the water main meets the required health and safety standards.
Upon successful completion of the flushing and chlorination process and contingent on favorable sampling results, the contractor will proceed with connecting domestic water services to the new main. Starting Friday, December 13, Cratus will begin installing new service connections, commencing at the 1300 block of West Texas Street, near Pennsylvania Avenue. From there, the team will progress eastward towards Curtis Drive to complete the service connections for local businesses and residents.
The Public Works Department appreciates the community's patience and understanding as this critical infrastructure improvement project advances. Notices have been sent to business and residents, impacted by the service disruption and you can expect minor service interruptions during the connection process, but every effort will be made to minimize disruptions.
For updates and additional information about the project, please contact the Public Works Department at (707) 428-7485.
West Texas Striping & Intersection Project
The West Texas Striping & Intersection Project meeting was held via zoom on February 16, 2022.
Please click here for the powerpoint presentation.
Should you have any questions, please contact Phil Layoso, Assistant Engineer at (707) 428-7505.
Memorandum for the Reconsideration of Relief Trunk Sewer
Community Workshops
- January 27, 2015: Community Workshop #1
- June 4, 2015: Community Workshop #2
- June 11, 2015: Booth at Downtown Farmers Market
- June 12, 2015 - June 30, 2015: Conducted Online Survey
- November 18, 2015: Community Open House #1
- December 1, 2021: Virtual Open House
- January 17, 2024: Community Open House #2
Project Contact
David Vong, Senior Civil Engineer
Public Works Department – Engineering
Phone: 707-428-7485
Email: completestreets@fairfield.ca.gov