Description: Annual street maintenance consisting of replacing existing and/or installing new ADA ramps as necessary, adding bike lanes, and surface seal coat treatment of approximately 1.75 million square feet of pavement
Status: Design complete, pending project bid in Winter 2021
Estimated Construction Schedule: April 2022 through July 2022
Description: Annual street maintenance consisting of replacing existing and/or installing new ADA ramps as necessary, adding bike lanes, and surface seal coat treatment of approximately 1.39 million square feet of pavement.
Status: Complete
Estimated Construction Schedule: July 2020 through November 2020
The sealing treatment is complete. The next phase of the project will include striping and concrete work around manholes, once clean up from the sealing treatment has been finished. There will be temporary partial lane closures throughout the duration of construction.
2019 Pavement Maintenance Project
Description: Annual street maintenance consisting of replacing existing non compliant ADA ramps as necessary, realigning crosswalks, and improving approximately 262,000 square feet of pavement.
Status: Complete
Estimated Construction Schedule: July 2019 through October 2019
Major construction work on Capitola Way and Air Base Parkway at Heath Drive is completed. Minor concrete work still needs to be finished.
2018 Pavement Maintenance Project Phase 2
Description: Annual street maintenance consisting of replacing existing and/or installing new ADA ramps as necessary, realigning crosswalks, traffic signal system adjustments, adding bike lanes, and rehabilitation of approximately 2 million square feet of pavement.
Status: Complete
Estimated Construction Schedule: August 2018 through October 2018
Description: Annual street maintenance consisting of replacing existing ADA ramps in areas with high volumes of pedestrian traffic, adding bike lanes, and surface seal coat treatment of approximately 4.27 million square feet of pavement.
Status: Complete
Estimated Construction Schedule: May 2018 through August 2018